Concrete Construction: STL Photo of the Week

Posted on October 19, 2018 in Photos

Construction on Arrivals Drive in Terminal 1 at St. Louis Lambert International Airport (STL) began this week, shifting passenger pickup locations for many. During phase one, lanes south of the center island on Arrivals Drive in Terminal 1 were closed to vehicular and pedestrian traffic. Passenger pickup was moved from the curb of Arrivals Drive to the yellow level of the Terminal 1 parking Garage. Rideshare (Uber & Lyft) pickup was also moved to Departures Drive, near exit 6. Phase one is expected to last four weeks. After phase one is completed, phase two will begin, with work being done on the lanes north of the center island. Phase two is also expected to last four weeks. For more details, including a map of all the temporary changes, visit www.flystl.com/news.