STL installing new LED lighting in Lindbergh Tunnel
Posted on October 23, 2020 in Media Releases
Project requires lane closure affecting traffic
ST. LOUIS (Oct. 23, 2020): St. Louis Lambert International Airport will begin installing new LED lighting in the Lindbergh Tunnel Monday, Oct. 26. The weeklong project requires the right lane of the northbound cell to be closed each day until 2:30 p.m.
Safety crews will begin setting up for the lane closure each morning at 9 a.m. During this time, the tunnel’s digital message boards will relay the current closure to drivers using Lindbergh.
If an additional day is needed for any uncompleted or delayed work, Friday, Oct. 30, has been selected as a contingency workday (see schedule below).
Monday Oct 26 Northbound Cell Right Lane Closed
Tuesday Oct 27 Northbound Cell Right Lane Closed
Wednesday Oct 28 Northbound Cell Right Lane Closed
Thursday Oct 29 Northbound Cell Right Lane Closed
*Friday, Oct. 30, reserved as a Contingency Day
###
For more information, please contact:
Roger Lotz 314-426-8125 (o)
314-795-2235 (c)