STL Begins Work on a Two-Year Runway Project

Posted on April 11, 2022 in Media Releases

Initial work on STL’s Runway 12R-30L will run until mid-September

ST. LOUIS, MO (April 11, 2022): Starting today, St. Louis Lambert International Airport (STL) begins construction on Runway 12R-30L. Runway 12R-30L runs from Banshee Road at its far northwest point to James S. McDonnell Boulevard.

Beginning today, Runway 12R-30L will be closed daily from 7 a.m. to 5 p.m. On April 18, the closure will expand to a continuous closure for the construction season.

This work will have operational impacts. For STL’s southeast air traffic, planes will now use Runway 12L as the primary departure runway and Runway 11 will be the primary runway for planes landing at STL from that direction. While the airport’s northwest air traffic will use Runway 29 for departures and Runway 30R will handle arrivals from that direction.        

This portion of the construction project will end in mid-September.

 ###

About STL

St. Louis Lambert International Airport (STL) is the primary commercial airport for the St. Louis metro area and parts of eastern Missouri and southern Illinois serving nearly 15.9 million passengers annually.  STL is an Enterprise Fund Department of the City of St. Louis. It is wholly supported by airport user charges. No general fund revenues are used for the operation, administration, promotion or maintenance of airport facilities. For more information on flights and services at St. Louis Lambert International Airport, log onto www.flystl.com.