Roadwork on Lambert International Boulevard to Begin July 17

Posted on July 13, 2018 in Media Releases

Roadway construction on Lambert International Boulevard (LIB) began on Tuesday, July 17. The construction project will require the closure of one lane on LIB, weather permitting. Traffic control signage and blockades will be in place to alert drivers of lane closures in the affected area. 

Circled in orange in the above map, work on the westbound lanes of LIB, east of the entrance to Terminal 2, will begin on Monday, July 30.  Work in this area is expected to be completed within two weeks. Eastbound lanes of LIB will not be affected during this time.

The construction being performed is part of routine roadway maintenance to replace aging slabs of concrete.  The entire project on LIB is expected to be completed within six weeks.